Project Background
The Santa Ynez Reservoir Floating Cover Project was being constructed to comply with two United States Environmental Protection Agency water quality regulations:
- Stage 2 Disinfectants and Disinfection By-Products Rule (S2DBPR)
- Long Term 2 Enhanced Surface Water Treatment Rule (LT2ESWTR)
In order to meet these two regulations, the LADWP did the following:
- Switch disinfectants from chlorine to chloramines
- Cover Santa Ynez Reservoir
Scope of Project
Major project components included:
- Removal of inlet/outlet tower and resurfacing of reservoir asphalt liner
- Construction of a blended green and black hypalon floating cover over the entire surface (~ 9.2 acres) of the reservoir
- Construction of new firefighting facilities at the Pacific Palisades Reservoir which includes a cistern
- Implementation of the Landscape Master Plan to mitigate the visual impacts of the floating cover. This includes:
- Rockwork and Planting on Slope Repair Area
- Reservoir Service Road Surface
- Resurface the perimeter road surface with a darker color to visually blend with the adjacent reservoir cover and surroundings
- Debris Retention Basin
- Resurface with same material/color as service road
- Helipad
- Resurface the helipad area with colored pavement to complement the adjacent reservoir
- Reservoir Dam Slope Treatment
- Naturalized drifts of native grasses will be introduced to dam faces to add color and texture to these areas
- Approach Road
- Resurface the access road and concrete swale with a darker color to visually blend with the adjacent reservoir cover and surrounding hillside
- Water Tank Removal and Infill Planting
Status
- Bid Opening: December 18, 2008
- Notice To Proceed: March 30, 2009
- Start of Construction: July 23, 2009
- First Drain of Reservoir: October 1, 2009 – May 1, 2010
- Demolish inlet/outlet tower and pipeline
- Repave reservoir asphalt liner
- Install new pipeline and appurtenances
- Second Drain of Reservoir: October 1, 2010 – May 1, 2011
- Install floating cover: January 2011
- Contract Complete: December 2011
- End of Construction: December 19, 2012
LADWP Contact Information
For questions regarding the construction of this project, please contact Mr. John Otoshi, Project Manager at (213) 367-0401, or by email at [email protected].
Updated January 31, 2013